Park Culvert - Pipeline Rd

Section:  19-00073-11-BR

Project:  Concrete Box Culvert Replacement

Start Date:  July 07, 2020

Status:  10% Complete

Completion Date:

Funding:  County Bridge Funds

Bid Cost:  $1,162,644.50

Cost to Date:  

Comments:  Removed Existing Pavement / Started Earthwork