Ron Smith Memorial Hwy

Section:  19-00123-02-RS

Project:  Cold-In-Place Recycling & Resurfacing from CH 31 to CH 8

Start Date:  July 07, 2020

Status:  90% Complete

Completion Date:

Funding:  MFT (Motor Fuel Tax) & County Matching

Bid Cost:  $1,892,380.39

Cost to Date:  $1,872,867.02

Comments:  All HMA (Hot-Mix Asphalt) work has been completed.  Guardrail and pavement reflectors need to be installed.