Brand II Bridge - Stringtown Rd

Section:  20-00057-12-BR

Project:

Start Date:  04/04/2022

Status:  15% Complete

Anticipated Completion Date:

Funding:

Bid Cost:  $1,744,130.37

Cost to Date:  $293,543.00

Comments:  Contractor is working to finish driving pile on west side of bridge.