Lake Spur Rd

Section:  22-00046-16-RS

Project:

Start Date:  04/17/2023

Status:  50% Complete

Completion Date:

Funding:

Bid Cost:  $2,085,329.00

Cost to Date:  $1,067,313.91

Comments:  Hot Mix Asphalt (HMA) removal, Bituminous Widening, & Binder Lift are complete, preparing for Surface Lift