Section: 22-00046-16-RS
Project:
Start Date: 04/17/2023
Status: 50% Complete
Completion Date:
Funding:
Bid Cost: $2,085,329.00
Cost to Date: $1,067,313.91
Comments: Hot Mix Asphalt (HMA) removal, Bituminous Widening, & Binder Lift are complete, preparing for Surface Lift